JURUPA VALLEY (CNS) - The westbound Pomona (60) Freeway between Riverside and Ontario is slated to be shut down tonight and through the weekend as part of a resurfacing project that got underway three months ago and should only require one more full closure before Thanksgiving.

For the sixth consecutive weekend, a closure is planned on the westbound 60, beginning at 10 p.m., between the 60/91/215 interchange in Riverside and Interstate 15 in Ontario, roughly 13 miles. The closure is not slated to be lifted until 5 a.m. Monday.

The 55-hour shutdown replicates what occurred over eight weekends on the eastbound side. Those closures started on July 26 and concluded Sept. 23.

The westbound closures are scheduled to wrap up on the weekend of Nov. 16-17. Caltrans noted that work will be suspended for Veterans Day weekend, as it was paused to accommodate Labor Day weekend travel on the eastbound side.

The agency's objective is to have all the freeway closures finished before the Holidays.

Officials said the rehabilitation work, which entails replacing slabs of degraded pavement, is moving twice as fast because of the closures, dubbed the “60 Swarm” in reference to multiple projects occurring over the next two years along the 60 freeway. Altogether, the swarm covers a 20-mile stretch, from Chino to downtown Riverside.

In addition to the shutdowns, intermittent and extended lane closures are occurring in the construction zone, between Euclid Avenue in Ontario and the 60/91/215. Part of the Interstate 15/Route 60 interchange in Ontario is being reconfigured for the swarm, as well.

Single lane closures began 14 weeks ago in several locations and will conclude in November 2021, when the $134 million pavement replacement project is supposed to be finished, according to Caltrans.

The other part of the 60 Swarm is comprised of bridge replacements, costing $23 million. According to Caltrans, the Benson Avenue, Monte Vista Avenue and Pipeline Avenue overcrossings in Chino are all due to be razed and replaced with new spans. Alternating east- and westbound lane closures for the bridge work started 13 weeks ago.

Most of the overnight closures are occurring between Ramona Avenue and Reservoir Street in Chino.

Officials said the current bridges were constructed with dimensions that make them prone to being bumped by oversized truck loads. Over the years, the repeated minor hits have had a cumulative impact, requiring the two-lane bridges to be replaced.

More information is available at www.60Swarm.com, or via the 60 Swarm hotline: 833-607-9276.