Eastbound 60 Closure Continues in Riverside County

Eastbound 60 Closure Continues in Riverside County

JURUPA VALLEY (CNS) - The eastbound Pomona (60) Freeway between Riverside and Ontario will remain shut down today and through Sunday for resurfacing work that was put on hold over the Labor Day holiday weekend to free up travel through the area.

Beginning at 10 p.m. Friday, crews closed the entire eastbound 60 between Interstate 15 in Ontario and the 60/91/215 interchange in Riverside, roughly 13 miles, with the intent of maintaining the closure until 5 a.m. Monday.

Two additional weekend closures on the eastbound 60 are scheduled this month, over the same 55-hour periods. The final eastbound closure is slated to end the morning of Sept. 23.

The first overnight closure of the westbound 60 is scheduled Sept. 27 and will also begin at 10 p.m., then end at 5 a.m. on Sept. 30. Officials said the westbound closures will continue over the ensuing seven weekends, ending Nov. 18. Work will be suspended for Veterans Day weekend. Caltrans' objective is to have all the freeway closures finished by Thanksgiving.

According to officials, several outdoor events last month in Fontana and Eastvale increased congestion on detour routes, including Interstates 10 and 15, but the delays were relatively minor.

Caltrans said the rehabilitation work, which entails replacing slabs of pavement, is moving twice as fast because of the partial closures, which Caltrans dubbed the “60 Swarm,” referring to multiple projects occurring over the next two years along the 60 freeway. Altogether, the swarm covers a 20-mile stretch, from Chino to downtown Riverside.

In addition to the shutdowns, intermittent and extended lane closures are occurring in the construction zone, between Euclid Avenue in Ontario and the 60/91/215, officials said, adding that portions of the Interstate 15/Route 60 interchange in Ontario is being periodically closed for the swarm, as well.

Single lane closures began six weeks ago in several locations and will wrap up in November 2021, when the $134 million pavement replacement project is slated to conclude, according to Caltrans.

The other part of the 60 Swarm is comprised of bridge replacements, costing $23 million. According to Caltrans, the Benson Avenue, Monte Vista Avenue and Pipeline Avenue overcrossings in Chino are all due to be razed and replaced with new spans. Alternating east- and westbound lane closures for the bridge work started five weeks ago.

Most of the overnight closures are occurring between Ramona Avenue and Reservoir Street in Chino.

Officials said the current bridges were constructed with dimensions that make them prone to being bumped by oversized truck loads. Over the years, the repeated minor hits have had a cumulative impact, requiring the two-lane bridges to be replaced.

More information is available at www.60Swarm.com, or via the 60 Swarm hotline: 833-607-9276.